6,000m³ Slurry Lagoon

Description


Bartlett Contractors were awarded the contract to design and excavate a new dirty water lagoon on a dairy farm near Dorchester, Dorset.

The 6,000m³ lagoon is double lined with a GCL bentonite layer underneath to form a leak detection system and a 1mm HDP liner on the surface. This ensures that the lagoon meets all environmental regulations.

Photos were taken during the finishing stages of the project, where the remains of the topsoil were going to be reinstated and graded and the fences around the perimeter of the lagoon, erected.

South East Water, Bray Pipeline

 

Description

We were called to finish the construction of the pipeline and testing due to the previous contractors business failing. Works included installation of 17km of 1200m welded steel pipe, 1200mm valves and fittings, live connections, repairs and realignments of existing pipe, testing and chlorination, full reinstatements of pipeline up to 5m deep.

Ground conditions varied from clay to running sand so temporary works were the main priority to get designed in front of works progressing.

Where large sections of the pipeline had previously been laid by the other contractor, a lot of the alignment of the pipe was so bad that V.J couplings could not stand the lateral pressure imposed on them. It was decided to remove all V.J couplings and to fit solid weld bands to hold the line in place and to mitigate any further leaks.

Large valve complexes and flow metres had to be fitted along the route of the pipeline which included civils works for building large concrete chambers and pipe supports. A total of 15 groundworkers/pipelayers worked on site alongside 7 x excavators, our experienced project manager, site foreman and site supervisors.

We did the testing of the pipeline in house due to the huge amount of leaks left by the previous contractor. Employing a testing contractor was not cost effective.

Sections of the pipeline crossed public roads and therefore streetworks and temporary traffic lights were put in place by trained employees. Where sections of the pipeline had failed on road crossings, the carriageway was excavated, temporary works installed, repair implemented and full carriageway reinstatement undertaken and inspected by local authorities.

The contract was a reactive situation due to the failing of the previous contractor leaving works unfinished and backfilled leading to a lot of leaks and broken apparatus.

 

 

Allen Hanford Ltd, Slurry Lagoon

 

Description

Excavated a 5,500m“ lagoon, top measurements 66m x 50m at 6m depth with the banks at 1 to 1. Installed underlay and liner and a leak detection system. Installed 4 no. concrete pads 6m x 4m x 150mm depth, 4 no. concrete pads in the base of the lagoon 3m x 3m and 4 no. 200mm suction pipes through the lagoon bank. Supplied and erected a galvanised chain link fence 1.8m high complete with corner strainers, 260Lm, 4 no. sets of galvanised palastrade double gates and 4 no. concrete stop blocks as a barrier to stop the stirring tractor from falling back into the lagoon.

 

 

 

 

 

Land and Water, Wick Flood Alleviation Scheme

 

Description

Working on behalf of Land and Water, Bartlett Contractors Ltd provided a stand alone sub-contract basis providing all necessary means to act as principal contractor to the Environment Agency.

The works consisted of construction of new embankments including cellular paving ramps, footpaths and block stone edging. Construction of new flood wall, raising of existing flood wall and trimming of existing close boarded fence. Raising of Wick Lane highway including new kerbs. Installing new palisade, timber post and rail and timber close boarded fencing. Installation of additional gullies and raising of existing gullies and manholes. Removal of trees, protection of trees and replanting of trees and shrubs. Installing precast concrete headwall and pipework for existing ditch. Relocating existing benches and water trough and all associated works.